North Canal Blvd/Martin Luther King Water Tower Painting Project
Louisiana > City of Thibodaux
Sealed Bid: 96522963
Listing Information/Advertisement:


ADVERTISEMENT FOR BIDS
 
The City of Thibodaux, Lafourche Parish, Louisiana, will receive ELECTRONIC BIDS for the North Canal Street/Martin Luther King Water Tower Painting project. All bids will be received electronically by the City of Thibodaux until 10:00 A.M. local time, on Monday, April 3, 2023, at which time bids will be retrieved from the Central Auction House (CAH) website and read aloud at City Hall, Council Chambers, 2nd Floor, 310 West 2nd Street, Thibodaux, LA 70301. Only electronic bids submitted on www.centralbidding.com will be  accepted.
 
Bid documents are posted on www.centralbidding.com. To view these, download, receive bid notices by e- mail, and submit the bid you must register with Central Auction House (CAH). Vendors/Contractors must submit their bids electronically. For information about the electronic submittal process, contact Central Auction House at 1-833-412-5717.
 
A mandatory Pre-Bid Conference will be held at 9:00 A.M. local time on Thursday, March 16, 2023 at the North Canal Street Water Tower, then move to the Martin Luther King Water Tower. The pre-bid conference will be conducted to discuss the Plans, Specifications, and project requirements.
 
The Contract Documents (Plans, Information for Bidders, Bid Form, Specifications and other pertinent documents) may be examined at the following location:
 
Process and Controls Engineering, LLC
9 Flamingo Street
New Orleans, Louisiana 70124
 
To qualify to bid, each bidder shall be a properly licensed Contractor in accordance with La. R.S. 37:2150 – 2163 for the classification of MUNICIPAL AND PUBLIC WORKS CONSTRUCTION.
 
The Owner reserves the right to reject any and all bids in accordance with Title 38 of the Louisiana Revised Statutes.
 
Each bidder must deposit with his/her bid, security in the amount, form and subject to the conditions provided in the Information for Bidders. Sureties used for obtaining bonds must appear as acceptable on the U.S. Department of Treasury Circular 570.
 
A bidder may withdraw their bid within forty-eight (48) hours of the bid opening, excluding Saturdays, Sundays and legal holidays as governed by La. R.S. 38:2214 (C).
 
Any questions or clarifications shall be submitted to the Project Engineer, Daniel T. Foglesong, in writing a minimum of five (5) days prior to the bid opening date. Addenda will be issued to all prospective bidders a minimum of 48 hours prior to the bid opening date. Only information provided within written addenda issued by the Project Engineer shall be considered binding.
 
Any person with disabilities requiring special accommodations must contact Thibodaux Council Administrators Office no later than seven (7) days prior to the bid opening.
 
                                                                                                                /s/Jennifer Morvant_____________________
                                                                                                                 Jennifer Morvant, Council Administrator
 
Publication Dates:  March 2, 2023
                               March 9, 2023
                               March 16, 2023
 

SUBMITTAL INFORMATION
Creator Username: cityofthibodaux
Bidding Privacy: Bid encryption
Started: 02-Mar-2023 12:00:00 AM CST
Ends: 10-Apr-2023 10:00:00 AM CDT ( Expired )
History: 1063 Views, 11 Messages
Event Status: Expired since 10-Apr-2023 10:00:00 AM CDT
Actions: Sign-In to Bid
Username:

Password:
Visitors: Visitors/Central Bidding Plan Holders
PUBLIC MESSAGE BOARD
Discuss questions with the owner/creator of this Listing.
precisioninspectionllc on 02-Mar-2023 8:43:02 AM CST
Could you please provide a physical address to each of the tanks.
cityofthibodaux on 02-Mar-2023 10:17:46 AM CST
1298 N. Canal Boulevard and 1445 Martin Luther King Drive are the addresses assigned to the Entergy meters for these towers.
precisioninspectionllc on 03-Mar-2023 7:49:06 AM CST
On the 1-million-gallon elevated tank will a dehumidification system required while blasting is performed on the interior.
precisioninspectionllc on 03-Mar-2023 7:53:42 AM CST
The completion days for this project is (160) days. Would it be possible to increase by (60) days?
cityofthibodaux on 06-Mar-2023 8:33:39 AM CST
On the 1-million-gallon elevated tank will a dehumidification system required while blasting is performed on the interior. The contractor needs to determine if a dehumidification system is required, and if required, should include the cost in the bid
cityofthibodaux on 06-Mar-2023 8:33:59 AM CST
The completion days for this project is (160) days. Would it be possible to increase by (60) days? 160 days should be sufficient for completion of the work. If work is delayed by causes outside of the Contractors control (weather, unavailability of the tank, other), extending the completion days can be evaluated at that time
Quality14 on 05-Apr-2023 1:06:50 PM CDT
are both tanks 1-million gallon?
cityofthibodaux on 05-Apr-2023 3:35:04 PM CDT
North Canal Street water tank is 500,000 gallons, Martin Luther King water tower is 1,000,000 gallons
Quality14 on 05-Apr-2023 6:11:53 PM CDT
Is there an estimated budget?
Quality14 on 05-Apr-2023 6:14:10 PM CDT
Did someone come and inspect to come up with an estimated budget?
cityofthibodaux on 10-Apr-2023 9:53:27 AM CDT
Per section 00 11 13 Advertisement for Bids, "Any questions or clarifications shall be submitted to the Project Engineer, Daniel T. Foglesong, in writing a minimum of five (5) days prior to the bid opening date. Addenda will be issued to all prospective bidders a minimum of 48 hours prior to the bid opening date. Only information provided within written addenda issued by the Project Engineer shall be considered binding." - These questions were not submitted 5 days prior to the bid opening date.
UPDATE/ADDENDUM HISTORY
All updates/changes are listed below::
04-Apr-2023 2:16:11 PM CDT
Addendum 3 Added
30-Mar-2023 10:16:08 AM CDT
Addendum 2 added-changes bid opening date to April 10, 2023
15-Mar-2023 3:21:10 PM CDT
Addendum 1 Added