OFFICIAL ADVERTISEMENT FOR BIDS
 
Sealed bids will be received by the Special Education Distr. No. 1 until 10:00 AM on Wednesday, October 25, 2023 in the Conference Room of The Center located at 5510 West Ave. D - West 55th St., Cut Off, LA 70345, at which time bids for the RENOVATIONS TO KITCHEN DRAIN LINES will be opened and publicly read aloud.
 
All bids shall be submitted in a sealed envelope bearing legibly on the exterior, the following:
 
            1.         Name of Owner
            2.         Name of Project
            3.         Louisiana Contractor's name, address, and state license number
 
All drawings, specifications and other Contract Documents for the project are available on the internet at www.centralbidding.com. No project Contract Documents will be provided by the Architect or Owner. Bids can be submitted electronically at www.centralbidding.com.
 
Each bid shall be accompanied by a bid security of not less than five (5%) percent of the total bid amount. Said amount shall be in the form of a Bid Bond, Certified Check, or Cashier’s Check drawn on a bank insured by the Federal Deposit Insurance Corporation payable to the Special Education District No. 1.
 
The successful lowest responsible and responsive bidder shall be required to furnish the Owner with a performance bond for 100% of the contract amount prior to the issuance of a contract to perform the work. No bid may be withdrawn for a period of 45 days after receipt of bids. The time of completion of this project is prime importance. The Bidder agrees to commence work under this contract not later than the date indicated in the Owner’s written Notice to Proceed. All of the work required shall be completed within 60 calendar days from the Notice to Proceed. Should the Contractor neglect, refuse or fail to complete the work on the amount of calendar days indicated above, the Owner shall have the right to deduct from and retain out of such moneys which may be due or which may become due and payable to the Contractor, as indicated in Article 9 of the Instructions to Bidders for each and every day that such completion of the work is delayed beyond the prescribed date / calendar days, as liquidated damages and not as a penalty. If the amount due and to become due from the owner to the Contractor is insufficient to pay in full any such liquidated damages, the contractor shall pay the owner the amount necessary to affect such payment in full. Provided, however, that the Owner shall promptly notify the Contractor in writing of the manner in which the amount retained, deducted, or claimed as liquidated damages was computed. Designer will be paid for prolonged contract administration and observation of construction should the contract time, as may be extended, be exceeded due to no fault of the Designer and liquidated damages are recommended by the Designer. The amount of such payment shall be computed by dividing 20% of the basic total fee by the number of days construction time, as extended to the contractural completion date, and multiplying by the number of days of liquidated damages recommended by the Designer. The Designer’s prolonged contract administration shall be compensated by deducting from moneys which may become due and payable to the Contractor.
 
Bids must be submitted on the Louisiana Uniform Public Works Bid Form furnished with the Bidding Documents. Bid sheets will be issued only to Contractors and/or Subcontractors licensed in accordance with the provisions of R.S. 37:2150 through 2173 of the Louisiana Legislature. Contractors desiring to bid shall submit their Louisiana Contractor’s License Number as evidence that they hold a license for BUILDING CONSTRUCTION that is in full force and effect.
 
A MANDATORY Pre-bid Conference will be held on Thursday, October 12, 2023, at 10:00 AM in the Conference Room of The Center. At the Mandatory Pre-Bid the design professional shall pass around a Sign-In Sheet prior to beginning the formal meeting. The sign-in sheet shall have an area to fill in the signature of the person representing a contractor, the company being represented, the Louisiana license number of the contractor, phone and fax number of the Contractor, and an email address of the Contractor. The Architect prefers that all of the five above items be filled out at the mandatory pre-bid. (The information required may be emailed to our office before or 24 hrs. after the Mandatory Pre-Bid at [email protected]. Emailing this information to our office shall not relieve the contractor of the requirement to be represented at the Mandatory Pre-Bid Conference.) The sign-in sheet shall be collected by the design professional prior to the completion of the meeting. Contractors shall not be allowed to sign the sign-in sheet after it is collected by the design professional. Contractors shall also be required to sign the sign-out sheet after the entire pre-bid conference is complete. (All Contractors shall sign the sign-in sheet and the sign-out sheet in order to bid this project.) Note:  Bids shall be accepted only from contractors that attended the entire Mandatory Pre-bid Conference. All questions from bidders shall be submitted by email to [email protected].  All questions sent by email shall have the project name in the subject area of the email. The last day to submit questions from the Mandatory Pre-bid Conference on this project is WEDNESDAY, OCTOBER 16, 2023, at 5:00 PM. The response to questions shall be WEDNESDAY, OCTOBER 18, 2023.
 
All drawings, specifications and other Contract Documents for the project are on file and open for review at the office of Gossen-Holloway-Cortez, 315 East Second Street, Thibodaux, Louisiana.
 
                                                                        Special Education District No. 1
                                                                        Torie Lee, Executive Director
                                                                        Peter Louviere, Pres., Bd. of Commissioners
 
 
 
ADVERTISEMENT DATES:
 
FIRST ADVERTISEMENT: TUESDAY, SEPTEMBER 26, 2023
SECOND ADVERTISEMENT: TUESDAY, OCTOBER 3, 2023
THIRD ADVERTISEMENT: TUESDAY, OCTOBER 10, 2023
 

Additional Notes/Requirements
The replumbing of the kitchen area of the main building on The Center campus as shown and described in the Contract Documents consists of the following: (This is a partial list. Refer to the rest of this specification and drawings for additional notes and information.) 1. This project entails the demolition and installation of new plumbing lines in the kitchen area of the main building on The Center campus. The existing plumbing has been found to be in corroding condition and near failure. 2. The replacement of the sanitary sewer piping shall be done by saw cutting the existing concrete slab and removing portions of the existing slab to access the sub grade and existing piping. The limits of work for areas that need to be saw cut are shown in the construction drawings.
SUBMITTAL INFORMATION
Creator Username: GHCARCHDB
Bidding Privacy: Bid encryption
Started: 26-Sep-2023 12:00:00 AM CDT
Ends: 25-Oct-2023 10:00:00 AM CDT ( Expired )
History: 223 Views
Event Status: Expired since 25-Oct-2023 10:00:00 AM CDT
Actions: Sign-In to Bid
Username:

Password:
Visitors: Visitors/Central Bidding Plan Holders
UPDATE/ADDENDUM HISTORY
All updates/changes are listed below::
18-Oct-2023 1:22:10 PM CDT
Addendum No. 3 - Modifications to Architectural and Mechanical Drawings
13-Oct-2023 11:06:23 AM CDT
Addendum No. 2 - mandatory pre-bid attendees
27-Sep-2023 11:29:34 AM CDT
Addendum No. 1 - Pre-Bid Information