SAP-55(58) - Bridge Replacement
Mississippi > Pearl River County
Solicitation: 55841982
Listing Information/Advertisement:


OFFICE OF STATE AID ROAD CONSTRUCTION
MISSISSIPPI DEPARTMENT OF TRANSPORTATION
AND
PEARL RIVER COUNTY BOARD OF SUPERVISORS
 
SECTION 900

NOTICE TO CONTRACTORS:

 
Sealed bids will be received by the Board of Supervisors of Pearl River County, Mississippi at the Pearl River County Courthouse, Poplarville, Mississippi, until 10:00 a.m. on the 12th day of June, 2018 and shortly thereafter publicly opened for the construction of 0.181 miles of BRIDGE REPLACEMENT on the OSCAR SMITH ROAD being known as Project No. SAP-55(58) in Pearl River County, Mississippi.  Electronic bids can be submitted at www.centralbidding.com.  For any questions relating to the electronic bidding process, please call 225-810-4814.
 
PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS:
 
ITEM                                                                            QUANTITY         UNIT
 
ROADWAY ITEMS:

MOBILIZATION                                                           LUMP SUM         LS
CLEARING AND GRUBBING                                     LUMP SUM         LS
REMOVAL OF BRIDGE AT STATION 49+99                        1.000         UN
REMOVAL OF PIPE (ALL SIZES)                                       80.000         LF
UNCLASSIFIED EXCAVATION (FM)                                 875.000        CY
BORROW EXCAVATION (F.M.E.)                                   2,580.000        CY
  (CONTRACTOR FURNISHED) (CLASS 7)
STRUCTURE EXCAVATION                                             625.000         CY
GRANULAR MATERIAL (LVM),                                     1,225.000         CY
  (CLASS 6, GROUP C)
SIZE II STABILIZER AGGREGATE,                                  350.000         CY
  COARSE
HOT MIX ASPHALT, ST 9.5 MM                                        258.000         TON
HOT MIX ASPHALT, ST 19 MM                                         540.000         TON
ASPHALT FOR PRIME COAT (EA-1)                                859.000         GAL
RIGHT-OF-WAY MARKERS (TYPE I)                                  14.000         EA
MAINTENANCE OF TRAFFIC                                      LUMP SUM        LS
ADDITIONAL CONSTRUCTION SIGNS                                0.000         SF
4" WIDE THERMOPLASTIC EDGE STRIPE                         0.364          MI
  (CONTINUOUS WHITE) (60 MILS)
4" WIDE THERMOPLASTIC TRAFFIC                           1,920.000           LF
  STRIPE (CONTINUOUS YELLOW)
  (90 MILS)
TWO-WAY YELLOW REFLECTIVE HIGH                          17.000            EA
  PERFORMANCE RAISED MARKERS
TEMPORARY STREAM DIVERSION                                   1.000            EA
 
EROSION CONTROL ITEMS:
AGRICULTURAL LIMESTONE                                             3.200            TON
COMMERCIAL FERTILIZER (13-13-13)                               1.600            TON
AMMONIUM NITRATE                                                          0.160            TON
SEEDING                                                                               1.600            AC
VEGETATIVE MATERIALS FOR MULCH                              3.200           TON
SOLID SODDING                                                               200.000           SY
EROSION CONTROL FABRIC                                           500.000           SY
TEMPORARY SILT FENCE                                             2,000.000           LF
  (TYPE II) (AOS 0.15-0.84)
LOOSE RIPRAP, 200 LB.                                                   210.000            TON
GEOTEXTILE UNDER RIPRAP,                                         410.000            SY
  TYPE V, AOS 0.21-0.43
WATTLES, 20"                                                                    200.000            LF
 
BOX BRIDGE ITEMS:
BOX BRIDGE CONCRETE, CLASS "BB"                          240.690            CY
REINFORCEMENT                                                        51,770.000            LB
 
 
PROJECT NO. SAP-55(58)
PEARL RIVER COUNTY
 
NOTICE TO CONTRACTORS:

CONTRACT TIME:             80 Working Days
 
BASIS OF AWARD
 
The award, if made, will be made to the lowest qualified bidder on the basis of published quantities.
 
The Board of Supervisors hereby notifies all bidders that it will affirmatively insure that in any contract entered into pursuant to this advertisement, minority business enterprise will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award.
 
PLANS AND SPECIFICATIONS are on file in the Office of the Chancery Clerk of Pearl River County, the County Engineer's office and the Office of the State Aid Engineer, 412 E. Woodrow Wilson Avenue, Jackson, Mississippi.  This project shall be constructed in accordance with the latest edition of the Mississippi Standard Specifications for State Aid Road and Bridge Construction.
 
PLANS AND PROPOSALS may be secured from H. Les Dungan, III, County Engineer for Pearl River County, Mississippi, 925 Goodyear Blvd, Picayune.  The Cost is fifty dollars ($50.00) for plans and fifty dollars ($50.00) for the proposal, non-refundable.  Or official bid documents can be downloaded from Central Bidding at www.centralbidding.com.
 
Certified check or bid bond for five percent (5%) of the total bid, made payable to Pearl River County and the State of Mississippi must accompany each proposal.
 
Bidders are hereby notified that any proposal accompanied by letters qualifying in any manner the condition under which the proposal is tendered will be considered an irregular bid and such proposal will not be considered in making the award.
 
Sandy Kane Smith, President
Pearl River County Board of Supervisors

SUBMITTAL INFORMATION
Creator Username: DunganEngLD
Bidding Privacy: Bid encryption
Started: 30-Apr-2018 3:43:09 PM CDT
Ends: 12-Jun-2018 10:00:00 AM CDT ( Expired )
History: 1230 Views
Event Status: Expired since 12-Jun-2018 10:00:00 AM CDT
Actions: Sign-In to Bid
Username:

Password:
Visitors: Visitors/Central Bidding Plan Holders
UPDATE/ADDENDUM HISTORY
All updates/changes are listed below::
07-May-2018 2:34:47 PM CDT
04-May-2018 7:56:55 AM CDT