ADVERTISEMENT FOR BIDS
Sealed Bids will be received at the office of Dr. Daniel Rawls, Superintendent, Webster Parish School Board, P. O. Box 520 (71058-0520), 1442 Sheppard Street (71055), Minden, Louisiana, until 2:00PM, Thursday, AUGUST 25, 2016 for
JOB# 2015-13
ADDITIONS & ALTERATIONS TO
J. A. PHILLIPS ELEMENTARY & WEBSTER JUNIOR HIGH SCHOOL
MINDEN, LOUISIANA
After stamping to acknowledge timely receipt, the proposals will be publicly opened and read aloud. Sole responsibility for proper mailing or delivery of any bid in compliance with this advertisement is that of the bidder. Any offer received after closing time will be returned unopened.
All bids must be accompanied by bid security equal to five percent (5%) of the Base Bid and all Alternates and must be in the form of a Certified Check, Cashier's Check or Bid Bond written by a company licensed to do business in the State of Louisiana.
Complete Bid Documents may be obtained from Yeager, Watson & Associates, Inc., An Architectural Corporation, 808 Versailles Boulevard, Alexandria, LA 71303-2377, (318) 445â??2446, upon deposit of $100.00 for each set of documents. The deposit is fully refundable to all planholders upon return of the documents, in good condition, no later than fifteen (15) days after receipt of bids. The deposit of all other sets returned after fifteen (15) days will be forfeited.
Bid related materials & electronic submittal of bids may also be found at WWW.CENTRALBIDDING.COM.
The Owner reserves the right to reject any and all bids and to waive any informalities incidental thereto.
WEBSTER PARISH SCHOOL BOARD
By /s/ Daniel Rawls
/t/ Daniel Rawls, Superintendent
Publication Dates:
July 21st, 2016
July 28th, 2016
August 4th, 2016
TO: General Contractors, Sub-Contractors, Manufacturer Reps & Plan Rooms
ESTIMATED COST: A/E opinion of probable construction cost is $5,900,000.00
PRE-BID CONFERENCE (Non-Mandatory): Starting at J. A. Phillips Elementary School, 811
Durwood Drive, Minden, LA 71055 at 9:30 AM local time, and moving to Webster Junior High School,
700 East Union Street, Minden, LA 71055 at 10:30 AM local time, Thursday, August 11, 2016.
BID DATE: 2:00 PM Thursday, 25th August, 2016 - Webster Parish School Board, 1442 Sheppard
Street; Minden, LA
This project is to be completed in 310 days.
PLAN DEPOSIT: $100.00 each set; refundable on submitting a bid & after contract documents are
safely returned by on/before September 9th, 2016
The project is located at both J. A. Phillips Elementary & Webster Jr. High School and includes the
following:
Base Bid: Includes all work at both campuses.
J. A. Phillips Elementary School:
< New Building D: Construction of a new Classroom Building for Kindergarten students, consisting of
a new detached single-story classroom wing.
< Existing Building A: Renovation work inside the existing School Building to upgrade and expand
restrooms, to subdivide large spaces for classrooms, and renovate other classrooms to be age-
appropriate.
< Site: Work consists of site clearing, grading, drainage, additional concrete parking paving, concrete
walkway and pad paving, fencing, and associated utility work.
Webster Junior High School:
< New Building J: Construction of a new Classroom & Multipurpose Building for 6th Grade students,
consisting of a new detached single story classroom wing with P.E. Gym.
< Existing Building F: Renovation work inside the existing Gymnasium to add telescoping bleachers
at both ends of the court. Also, fill in the recessed floor at the Cafeteria/Auditorium.
< Existing Building G: Renovation work inside the existing School Building to outfit a vacant room
as a new Computer Lab.
< Existing Building H: Renovation work inside the existing Classroom Building to combine two
classrooms and expand the restroom and cleanup area for Special Education students.
< Site: Work consists of site clearing, grading, drainage, additional asphalt parking paving, concrete
walkway and pad paving, fencing, and associated utility work.
Alternate No. 1: Add an Aluminum Unloading Cover and associated concrete walk expansion to the
East side of the Webster Junior High campus.
Note to Contractors: This project also includes a CONTRACTOR OPTION to construct the Phillips
Building D utilizing a modular concrete building system as manufactured by Fibrebond Corp.,
Minden, LA, or approved equal system. The project is designed to use “conventional” building
systems, or at the Contractor’s Option, to use the Fibrebond product for the structural shell of the
building.
Our associates on this commission:
MECHANICAL & ELECTRICAL: GUTH & ASSOCIATES, INC., 209 Milam Street, Shreveport, LA
71101; Telephone (318) 221–8638 FAX (318) 221-8717
STRUCTURAL ENGINEER: FERGUS ENGINEERING; 801 Westbourn Court, Fort Collins, CO
80525; Telephone (970) 568-8489; FAX (970) 568-8489