Fish Lab Complex, Rockefeller Wildlife Refuge
Louisiana > Facility Planning and Control - Division of Administration
Sealed Bid: 11472397
Listing Information/Advertisement:


The Work of Project is defined by the Contract Documents and consists of the following:
Concrete pile, beam foundation system.
Hollow core plank floor.
Steel sheet pile retaining system.
Prefabricated metal building structure.
Standing seam metal roof.
Lab: High efficiency ductless HVAC system with makeup air units.
Incubator: Preheated makeup air exchange.
Closed cell spray foam insulation.
Preheated water supply system – expandable.
Water treatment plant – expandable.
Emergency backup generator system – rough-in only. Generator equipment, fuel tank and platform to be installed at a future date.
High efficiency lighting fixtures

SUBMITTAL INFORMATION
Creator Username: ABM
Bidding Privacy: Bid encryption
Started: 10-Nov-2016 12:00:00 AM CST
Ends: 13-Dec-2016 2:00:00 PM CST ( Expired )
History: 1663 Views
Event Status: Expired since 13-Dec-2016 2:00:00 PM CST
Actions: Sign-In to Bid
Username:

Password:
Visitors: Visitors/Central Bidding Plan Holders
UPDATE/ADDENDUM HISTORY
All updates/changes are listed below::
08-Dec-2016 1:50:40 PM CST
addenda no. 2
08-Dec-2016 10:00:28 AM CST
added geotech report
07-Dec-2016 2:31:00 PM CST
added addenda no. 1